Update as of October 23, 2018:

 Sitework
 Mobilization and construction entrance
 Construction access road
 Initial erosion control and ponds/ditches
 Topsoil stripping and clearing
 Sanitary sewer line re-routing started and is only lacking the final tie in
 Waterline re-routing started and is only lacking the final tie in - scheduled for November 3
 Building pad construction started in a very limited capacity
 
 